A 660 MW coal-fired project is ready, power generation will start soon.

1320MW Coal Fired Power Project Jamshoro 660MW project has been completed and procurement of coal has been started for it.

Coal Fired 1320 MW Coal Fired Power Project Jamshoro First Phase 660 MW Coal Fired Power Project has been completed which will start generating electricity soon. has come.

More than 13 crore rupees are being continuously paid as interest on the loan taken from the Asian Bank. As soon as the former project director Mahesh Kumar retired, Bashir Ahmed Babbar was appointed as the project director in his place.

In the coal project, 6,500 tons of coal is being received on a daily basis, while according to the agreement, 80% of the coal from foreign countries and 20% from Thar were to be used in the power project, but no steps have been taken so far for Thar’s coal. According to the media, according to the former project director Mahesh Kumar, there is no railway line from Chhoor city to Islamkot, from where will the coal of Thar reach here, coal worth 12 billion rupees is being bought monthly.